The Common Application Form (CAF) is to be utilized when seeking clearances from the appropriate state department authorities. The submission of the CAF online, accompanied by a Self-Certification certificate, requisite fees, documents as well as necessary enclosures and attachments are required. Nevertheless, the CAF can be filled out manually with the assistance of the Nodal agency. The fees for submitting the application form are to be adhered in accordance with the guidelines set by the state government.
Sl No |
Approval |
Department |
Time Limits |
1 |
Consent for Establishment (CFE) (under water Act 1974 and Air Act 1981) | TSPCB | Green – 7 days; Orange – 14 Days; Red – 21 Days (Not requiring clearance from central government) |
2 |
Power feasibility & Estimate | DISCOMs (TSSPDCL OR TSNPDCL) | 2 Days for feasibility 10 days for estimate |
a) Up to 33KVA connection | DISCOMs (TSSPDCL OR TSNPDCL) | 2 Days for feasibility 10 days for estimate | |
b) above 33KVA connection | TSTRANSCO | 25 Days | |
3 |
Factory Plans Approval | Factories Departments | 7 Days |
4 |
Plot Allotment | TSIIC | 7 days |
5 |
Land Alienation | CCLA | 30 Days |
6 |
Change of Land use | CCLA under NALA Act | 14 Days |
7 |
Change of Land use | HMDA, KUDA and DTCP | 30 Days |
8 |
Layout & Industrial Building Plan | DT&CP / IALA/HMDA/KUDA | 7 Days for DT&CP; 14 Days for HMDA / KUDA/IALA; Pre-Scrutiny- 7 days; Approval – 7 Days for issuing proceeding and approved documents |
9 |
Provisional FIRE NOC | Fire Services Departments | Less than 15mts exempted from taking FIRE NOC and Occupancy 14 Days for Buildings more than 15mts height |
10 |
Permission to draw water (Borewell Permission) | Ground Water Department | 14 Days |
11 |
Feasibility of Water Supply | HMWS & SB Irrigation & CAD Department, CDMA, PR&RD, I%C, RWS, GHMC | 14 Days |
12 |
Vat Registration | Commercial Taxes Department | 1 Day in Hyderabad and 3 Days in districts |
13 |
License to store RS, DS | Excise Department | 14 Days |
14 |
Firm Registration | Registration & Stamp Department | 7 Days |
15 |
Authorization under hazardous waste | TSPCB | 21 Days |
16 |
NOC for Explosive License | The District collector | 7 Days |
17 |
NOC for Change of Land | The District collector | 7 Days |
18 |
NOC for Change of Land | Irrigation Department | 7 Days |
19 |
Permission for felling non- exempted tress under AP WALTA Act | Forest Department | 15 Days |
20 |
Registration of Principle employer’s establishment under provision of The Contracts Labour (Regulation and Abolition) Act 1970 | Labour, Employment, Training & Factories Department (LET & F Department) | 30 Days |
21 |
License for Contractors under provision of The Contracts Labour (Regulation and Ambition) Act 1970 | LET&F | 30 Days |
22 |
Registration under the Building and other Construction Workers (Regulation of Employment and Conditions of Service) Act1996 | LET&F | 15 Days |
23 |
Regulation of Establishment under Inner state Migrants Workmen (RE&CS) Act, 1979 | LET&F | 30 Days |
24 |
Electrical Design Approval | CEIG | 14 Days |
25 |
Professional Tax Registration | Commercial Taxes Department | 1 Day |
Sl No | Clearance | Department | Time Limits |
1 | Consent for Operation (CFO) (Under Water Act 1974 and Air Act 1981) | TSPCB | Green – 7 Days; Orange – 14 Days; Red – 21 Days (not requiring Central Government Clearances) |
2 | Factory License | Factories Department | 7 Days |
3 | Fire Occupancy Certificate | Fire Service Department | 14 Days (for buildings more than 15 Mts. Height) |
4 | Electrical Installation Certificate | Chief Electrical Inspectorate | 6 Days |
5 | Boiler Registration | Boilers Department | 14 Days |
6 | Drug Manufacturing License | Drug Control Administration | 14 Days |
7 | Registration under the Legal Metrology Act, 2009 | Consumer Affairs, Food & Civil Supplies | 15 Days |
8 | Registration under Shops and Establishment Act | LET & F | 1 Day |
9 | Registration of Establishment under the Inner State Migrants Workmen (RE&CS) Act, 1979 | LET & F | 30 Days |
10 | Final Completion / Occupancy Certificate | DT&CP / IALA / HMDA / KUDA / UDAs | 8 Days |
11 | Registration of Steam Pipe Line from Boilers Department | Boilers Department | 14 Days |